πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Chapman Ranch Wind 345 Phase II

Chapman Ranch Wind 345 Phase II is a 249 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12INR0035
Grid region
ERCOT (Texas)
Developer
Element Markets
Technology
Wind: 249 MW
Total requested
249 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
4 September 2009
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in