πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OTHER Β· PJM

Other project AC2-034

Other project AC2-034 is a 100 MW other request withdrawn in the PJM interconnection queue, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC2-034
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Eugene-Dequine 345kV
Technology
Other: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
3 February 2017
Withdrawn
March 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem