United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
BATTERY STORAGE Β· SOUTHEASTBattery storage project 20230829017, Colleton County
Battery storage project 20230829017, Colleton County is a 300 MW battery storage request withdrawn in the Southeast interconnection queue, in Colleton County, South Carolina, connecting to Dominion Energy South Carolina.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20230829017
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Connection point (POI)
- Candays - Yemassee 230 kV
- Location
- Colleton County, South Carolina
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Proposed online date
- March 2026
Location
Marker shows the centre of Colleton County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Colleton County
- Gas project 283, Colleton CountyGas Β· 819 MW Β· in study
- Gas project 284, Colleton CountyGas Β· 819 MW Β· in study
- Gas project 285, Colleton CountyGas Β· 819 MW Β· in study
- Gas project 301, Colleton CountyGas Β· 458 MW Β· in study
- Gas project 300, Colleton CountyGas Β· 458 MW Β· in study
- Gas project 20240829009, Colleton CountyGas Β· 338 MW Β· in study
- Gas project 20240829010, Colleton CountyGas Β· 338 MW Β· in study
- Gas project 20240829011, Colleton CountyGas Β· 338 MW Β· in study
- Solar + storage project 20240829004, Colleton CountySolar + storage Β· 250 MW Β· in study
- Gas project 303, Colleton CountyGas Β· 208 MW Β· in study
- Gas project 302, Colleton CountyGas Β· 208 MW Β· in study
- Solar project 20190729002, Colleton CountySolar Β· 200 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem