πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project 517, Garves County

Solar + storage project 517, Garves County is a 120 MW solar + storage request withdrawn in the Southeast interconnection queue, in Garves County, Kentucky, connecting to Tennessee Valley Authority.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
517
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Location
Garves County, Kentucky
Technology
Solar: 120 MW Β· Battery
Total requested
120 MW
Queue status
Withdrawn
Entered queue
31 August 2022

Location

Marker shows the centre of Garves County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Garves County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem