United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTPapalote Creek Wind Farm
Papalote Creek Wind Farm is a 180 MW onshore wind request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 08INR0012a
- Grid region
- ERCOT (Texas)
- Developer
- Airtricity, Inc
- Connection point (POI)
- PAP1_PAP1 34.500
- Technology
- Wind: 180 MW
- Total requested
- 180 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 31 May 2006
- Agreement signed
- 29 August 2008
- Proposed online date
- September 2009
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem