🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

BATTERY STORAGE · SOUTHEAST

Battery storage project 309, Dorchester County

Battery storage project 309, Dorchester County is a 199 MW battery storage request in interconnection study in the Southeast interconnection queue, in Dorchester County, South Carolina, connecting to Santee Cooper.

Queue statusIn planning
  1. PlanningQueued May 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
309
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Santee Cooper
Location
Dorchester County, South Carolina
Technology
Battery: 199 MW
Total requested
199 MW
Service type
Network resource (NRIS)
Study phase
2025 Cluster
Queue status
Active
Entered queue
29 May 2025
Proposed online date
December 2028

Location

Marker shows the centre of Dorchester County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Dorchester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem