Rentech Project is a 16.0 MW gas request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jun 2011 (completed)
  2. ConsentedFeb 2013 (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
13INR0040
Grid region
ERCOT (Texas)
Developer
Agrifos Fertilizer, Inc
Technology
Gas: 16.0 MW
Total requested
16.0 MW
Study phase
IA
Queue status
Operational
Entered queue
1 June 2011
Agreement signed
25 February 2013
Proposed online date
November 2014
Came online
December 2014

Location

No county location in the queue data.

Power plants in Β· Transmission lines in