SOLAR Β· MISOSolar project J2284, Coahoma County
Solar project J2284, Coahoma County is a 66.0 MW solar request withdrawn in the MISO interconnection queue, in Coahoma County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2284
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI, LLC.
- Connection point (POI)
- Clarksdale-Delta 115kV line
- Location
- Coahoma County, Mississippi
- Technology
- Solar: 66.0 MW
- Total requested
- 66.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 8 September 2021
- Proposed online date
- December 2025
- Withdrawn
- October 2023
Location
Marker shows the centre of Coahoma County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Coahoma County
- Solar project J4073, Coahoma CountySolar Β· 200 MW Β· in study
- Solar project J1988, Coahoma CountySolar Β· 121 MW Β· withdrawn
- Solar project J2428, Coahoma CountySolar Β· 100 MW Β· withdrawn
- Solar + storage project J2771, Coahoma CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project J1957, Coahoma CountySolar Β· 90.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem