Onshore wind project G0292, Benton County

Onshore wind project G0292, Benton County is a 180 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0292
Grid region
West (non-ISO utilities)
Connection point (POI)
Prosser 115 kV Substation
Location
Benton County, Washington
Technology
Wind: 180 MW
Total requested
180 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
17 October 2007
Proposed online date
July 2011

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem