πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

GAS Β· MISO

Gas project G141, Le Sueur County

Gas project G141, Le Sueur County is a 46.0 MW gas request withdrawn in the MISO interconnection queue, in Le Sueur County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedFeb 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G141
Grid region
MISO (Midcontinent)
Connection point (POI)
Loon Lake - Loon Tap 115kV
Location
Le Sueur County, Minnesota
Technology
Gas: 46.0 MW
Total requested
46.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 October 2001
Agreement signed
20 February 2004
Proposed online date
January 2007

Location

Marker shows the centre of Le Sueur County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem