United States βΊ Grid βΊ Interconnection queues βΊ New York
OTHER Β· NYISOCherry Valley Wind Park
Cherry Valley Wind Park is a 40.5 MW other request withdrawn in the NYISO interconnection queue, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2002 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 114
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Global Winds Harvest, Inc.
- Connection point (POI)
- East Springfield
- Location
- New York
- Technology
- Other: 40.5 MW
- Total requested
- 40.5 MW
- Queue status
- Withdrawn
- Entered queue
- 22 April 2002
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem