Battery storage project Q44a is a 100 MW battery storage request built and operating in the West interconnection queue.

Queue statusOperating
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q44a
Grid region
West (non-ISO utilities)
Connection point (POI)
Vah-Ki 230 kV
Technology
Battery: 100 MW
Total requested
100 MW
Study phase
In-Service
Queue status
Operational
Entered queue
26 April 2018
Proposed online date
December 2023
Came online
December 2023

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem