πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Carya Solar

Carya Solar is a 42.0 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0046
Grid region
ERCOT (Texas)
Developer
Sun Edison
Technology
Solar: 42.0 MW
Total requested
42.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
1 October 2013
Proposed online date
October 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem