ONSHORE WIND Β· ERCOT

Senate Wind Project

Senate Wind Project is a 150 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued May 2006 (completed)
  2. ConsentedFeb 2009 (completed)
  3. Construction (completed)
  4. OperatingDec 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
08INR0011
Grid region
ERCOT (Texas)
Developer
Gamesa Energy USA
Connection point (POI)
FG_SENATE_G134.500
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
IA
Queue status
Operational
Entered queue
30 May 2006
Agreement signed
13 February 2009
Proposed online date
December 2012
Came online
December 2012

Location

No county location in the queue data.

Power plants in Β· Transmission lines in