πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Hubbard West Wind

Hubbard West Wind is a 201 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0039
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
3406 Elm Mott 345kV + 13mi gen tie
Technology
Wind: 201 MW
Total requested
201 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
3 April 2017
Proposed online date
December 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem