SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-809

Solar + storage project IC-809 is a 220 MW solar + storage request withdrawn in the Southeast interconnection queue, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-809
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Millers Ferry - Sunny South 115kv Line
Technology
Solar: 220 MW Β· Battery
Total requested
220 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
1 October 2019
Withdrawn
January 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem