OTHER Β· NYISO

Sunset Energy Fleet

Sunset Energy Fleet is a 520 MW other request withdrawn in the NYISO interconnection queue, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 1999 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
6
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
Sunset Energy Fleet LLC
Connection point (POI)
Gowanus
Location
New York
Technology
Other: 520 MW
Total requested
520 MW
Queue status
Withdrawn
Entered queue
17 February 1999

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem