ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-148, Newton County

Onshore wind project GEN-2017-148, Newton County is a 202 MW onshore wind request withdrawn in the SPP interconnection queue, in Newton County, Missouri, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-148
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Connection point (POI)
Joplin 161kV sub
Location
Newton County, Missouri
Technology
Wind: 202 MW
Total requested
202 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
27 November 2017
Proposed online date
December 2026
Withdrawn
October 2023

Location

Marker shows the centre of Newton County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Newton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem