United States › Grid › Interconnection queues › South Carolina
SOLAR + STORAGE · SOUTHEASTSolar + storage project 20240829001, Richland County
Solar + storage project 20240829001, Richland County is a 250 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Richland County, South Carolina, connecting to Dominion Energy South Carolina.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 20240829001
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Connection point (POI)
- Wateree - Hopkins 230 kV #2
- Location
- Richland County, South Carolina
- Technology
- Solar: 250 MW · Battery
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Proposed online date
- December 2028
Location
Marker shows the centre of Richland County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Richland County
- Solar + storage project 20240829013, Richland CountySolar + storage · 74.9 MW · in study
- Solar project 268, Richland CountySolar · 51.0 MW · in study
- Solar project 72, Richland CountySolar · 75.0 MW · built
- Solar + storage project 20210901001, Richland CountySolar + storage · 600 MW · withdrawn
- Solar + storage project 20220118001, Richland CountySolar + storage · 450 MW · withdrawn
- Solar + storage project 20220504001, Richland CountySolar + storage · 400 MW · withdrawn
- Solar + storage project 20220601002, Richland CountySolar + storage · 400 MW · withdrawn
- Battery storage project 20220228001, Richland CountyBattery storage · 200 MW · withdrawn
- Battery storage project 20240829002, Richland CountyBattery storage · 125 MW · withdrawn
- Solar project 141, Richland CountySolar · 125 MW · withdrawn
- Solar project 20171018009, Richland CountySolar · 100 MW · withdrawn
- Solar project 20171018006, Richland CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem