Central Heating & Refrigeriation Facility 1 & 2

Central Heating & Refrigeriation Facility 1 & 2 is a 10.0 MW gas request built and operating in the PJM interconnection queue, connecting to PEPCO.

Queue statusOperating
  1. PlanningQueued Jul 2000 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2004 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
D09
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
9th St (sub 117) 13kV
Location
District of Columbia
Technology
Gas: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
24 July 2000
Proposed online date
June 2004
Came online
June 2004

Location

No county location in the queue data.

Power plants in District of Columbia · Transmission lines in District of Columbia

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem