United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

OTHER Β· NYISO

NU CT-LI HVDC Cable

NU CT-LI HVDC Cable is a 660 MW other request withdrawn in the NYISO interconnection queue, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
101
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Northeast Utilities Service Co.
Connection point (POI)
Shore Road
Location
New York
Technology
Other: 660 MW
Total requested
660 MW
Queue status
Withdrawn
Entered queue
13 July 2001

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem