BATTERY STORAGE · NYISO

Crossbuck Energy Storage LLC

Crossbuck Energy Storage LLC is a 100 MW battery storage request withdrawn in the NYISO interconnection queue, in Greene County, New York, connecting to CHG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1471
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
Crossbuck Energy Storage LLC
Connection point (POI)
Coxsackie 69 kV substation
Location
Greene County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Withdrawn
Entered queue
22 November 2022

Location

Marker shows the centre of Greene County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Greene County