MeadWestvaco Covington Mill Site

MeadWestvaco Covington Mill Site is a 30.0 MW other request built and operating in the PJM interconnection queue, in City Of Covington County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Jun 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
X2-060
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
East Mill 138kV
Location
City Of Covington County, Virginia
Technology
Other: 30.0 MW
Total requested
30.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 June 2011
Proposed online date
June 2014
Came online
October 2013

Location

Marker shows the centre of City Of Covington County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem