SOLAR Β· WEST

Solar project 1085, Sublette County

Solar project 1085, Sublette County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Sublette County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1085
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Chimney Butte substation
Location
Sublette County, Wyoming
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Request moved to transition cluster
Queue status
Withdrawn
Entered queue
13 November 2018
Proposed online date
November 2020

Location

Marker shows the centre of Sublette County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Sublette County