Quail Run Energy Center 1

Quail Run Energy Center 1 is a 275 MW coal request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued May 2005 (completed)
  2. ConsentedMar 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Apr 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
06INR0036b
Grid region
ERCOT (Texas)
Developer
Navasota Energy LLC
Connection point (POI)
QALSW_GT1 13.800
Technology
Coal: 275 MW
Total requested
275 MW
Study phase
IA
Queue status
Operational
Entered queue
11 May 2005
Agreement signed
10 March 2006
Proposed online date
April 2007

Location

No county location in the queue data.

Power plants in Β· Transmission lines in