United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
SOLAR Β· SOUTHEASTSolar project 962982, Laurens County
Solar project 962982, Laurens County is a 60.0 MW solar request withdrawn in the Southeast interconnection queue, in Laurens County, South Carolina, connecting to Duke Energy Carolinas.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 962982
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Carolinas
- Connection point (POI)
- CLINTON BL 100kV
- Location
- Laurens County, South Carolina
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Other
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 27 September 2024
Location
Marker shows the centre of Laurens County; the queue data does not give exact sites.
Power plants in South Carolina Β· Transmission lines in South Carolina
Other requests in Laurens County
- Solar project 164382, Laurens CountySolar Β· 37.5 MW Β· agreement signed
- Solar project 963122, Laurens CountySolar Β· 50.0 MW Β· in study
- Solar project 131, Laurens CountySolar Β· 160 MW Β· withdrawn
- Solar project 918639, Laurens CountySolar Β· 74.9 MW Β· withdrawn
- Solar project 63666, Laurens CountySolar Β· 55.0 MW Β· withdrawn
- Solar project 564376, Laurens CountySolar Β· 50.0 MW Β· withdrawn
- Solar project 126078, Laurens CountySolar Β· 40.0 MW Β· withdrawn
- Solar project 165980, Laurens CountySolar Β· 37.5 MW Β· withdrawn
- Solar project 957065, Laurens CountySolar Β· 18.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem