🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › South Carolina

BATTERY STORAGE · SOUTHEAST

Battery storage project 20230829013, Berkeley County

Battery storage project 20230829013, Berkeley County is a 199 MW battery storage request in interconnection study in the Southeast interconnection queue, in Berkeley County, South Carolina, connecting to Dominion Energy South Carolina.

Queue statusIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
20230829013
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Dominion Energy South Carolina
Connection point (POI)
Williams - Goose Creek 230 kV
Location
Berkeley County, South Carolina
Technology
Battery: 199 MW
Total requested
199 MW
Service type
Network resource (NRIS)
Queue status
Active
Proposed online date
December 2028

Location

Marker shows the centre of Berkeley County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Berkeley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem