πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OTHER Β· PJM

Other project V4-030

Other project V4-030 is a 350 MW other request built and operating in the PJM interconnection queue, connecting to ComEd.

Queue statusOperating
  1. PlanningQueued Dec 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V4-030
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Byron 2-NI Hub
Technology
Other: 350 MW
Total requested
350 MW
Service type
Energy only (ERIS)
Study phase
Available studies: System Impact Study, Facilities Study
Queue status
Operational
Entered queue
8 December 2009
Proposed online date
May 2012

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem