Onshore wind project G792, Big Stone County

Onshore wind project G792, Big Stone County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Big Stone County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G792
Grid region
MISO (Midcontinent)
Connection point (POI)
Johnson Station facilities
Location
Big Stone County, Minnesota
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
30 April 2007
Agreement signed
25 July 2012
Proposed online date
June 2009
Withdrawn
July 2012

Location

Marker shows the centre of Big Stone County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Big Stone County