COAL Β· ERCOT

J K Spruce 2

J K Spruce 2 is a 750 MW coal request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Apr 2004 (completed)
  2. ConsentedMay 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2050 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
09INR0002
Grid region
ERCOT (Texas)
Developer
City Public Service of San Antonio
Connection point (POI)
CALAVER_JKS124.000
Technology
Coal: 750 MW
Total requested
750 MW
Study phase
IA
Queue status
Operational
Entered queue
13 April 2004
Agreement signed
23 May 2006
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem