ONSHORE WIND · MISOOnshore wind project H007, Delaware County
Onshore wind project H007, Delaware County is a 41.0 MW onshore wind request built and operating in the MISO interconnection queue, in Delaware County, Iowa.
Request details
- Queue ID
- H007
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Edgewood 69 kV Substation
- Location
- Delaware County, Iowa
- Technology
- Wind: 41.0 MW
- Total requested
- 41.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 22 April 2008
- Agreement signed
- 30 April 2010
- Proposed online date
- October 2015
- Came online
- October 2015
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Other requests in Delaware County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem