United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

GAS Β· NYISO

130 MW Uprate

130 MW Uprate is a 130 MW gas request withdrawn in the NYISO interconnection queue, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2005 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
202
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
Liberty Generating Co.
Connection point (POI)
Goethal 345kV
Location
New York
Technology
Gas: 130 MW
Total requested
130 MW
Queue status
Withdrawn
Entered queue
25 August 2005
Withdrawn
March 2019

Location

No county location in the queue data.