ONSHORE WIND Β· ERCOTOld Settler Wind
Old Settler Wind is a 150 MW onshore wind request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 16INR0037b
- Grid region
- ERCOT (Texas)
- Developer
- Apex Clean
- Connection point (POI)
- 79505 White River 345kV
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 24 February 2014
- Agreement signed
- 3 August 2015
- Proposed online date
- February 2017
- Came online
- April 2017