BATTERY STORAGE Β· ERCOT

Hecate Energy Roseland Storage 1

Hecate Energy Roseland Storage 1 is a 100 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0268
Grid region
ERCOT (Texas)
Developer
Hecate Energy Roseland Storage 1 LLC
Connection point (POI)
tap 345kV 3390 Jewett S - 3399 Ratsnake
Technology
Battery: 100 MW
Total requested
100 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
December 2022

Location

No county location in the queue data.

Power plants in Β· Transmission lines in