United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Sweetwater Wind 4

Sweetwater Wind 4 is a 300 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jan 2006 (completed)
  2. ConsentedJan 2007 (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0023
Grid region
ERCOT (Texas)
Developer
DKR Wind Holdings LLC
Connection point (POI)
SWEETW_WND4A34.500
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IA
Queue status
Operational
Entered queue
18 January 2006
Agreement signed
30 January 2007
Proposed online date
March 2007

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem