🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

ONSHORE WIND · ERCOT

Ocotillo Wind Farm 1 (Big Spring Option B)

Ocotillo Wind Farm 1 (Big Spring Option B) is a 59.0 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Sep 2003 (completed)
  2. ConsentedSep 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Aug 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
04INR0017
Grid region
ERCOT (Texas)
Developer
Texas American Power
Connection point (POI)
OWF_OWF 34.500
Technology
Wind: 59.0 MW
Total requested
59.0 MW
Study phase
IA
Queue status
Operational
Entered queue
15 September 2003
Agreement signed
12 September 2006
Proposed online date
August 2008

Location

No county location in the queue data.

Power plants in · Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem