πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

SOLAR Β· WEST

Solar project 75, Sanders County

Solar project 75, Sanders County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Sanders County, Montana, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
75
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Hot Springs - Noxon 230 kV line
Location
Sanders County, Montana
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
20 November 2018
Proposed online date
December 2020

Location

Marker shows the centre of Sanders County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Sanders County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem