SOLAR Β· WESTSolar project GI-2010-6, Boone County
Solar project GI-2010-6, Boone County is a 20.0 MW solar request withdrawn in the West interconnection queue, in Boone County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2010 (completed)
- Withdrawn / abandonedJan 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2010-6
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Boone Substation
- Location
- Boone County, Colorado
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- NRIS and ERIS
- Study phase
- Feasibility Study complete Request Withdrawn 1/12/12
- Queue status
- Withdrawn
- Entered queue
- 18 March 2010
- Proposed online date
- December 2011
- Withdrawn
- January 2012