🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

North Shenandoah-Stanley 34.5kV

North Shenandoah-Stanley 34.5kV is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Page County, Virginia, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD1-085
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
North Shenandoah-Stanley 34.5 kV
Location
Page County, Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
15 September 2017
Proposed online date
September 2026
Withdrawn
August 2024

Location

Marker shows the centre of Page County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Page County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem