United States βΊ Grid βΊ Interconnection queues
GAS Β· ERCOTCALHOUN (Port Comfort)
CALHOUN (Port Comfort) is a 100 MW gas request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 16INR0009
- Grid region
- ERCOT (Texas)
- Developer
- Castleman Power
- Connection point (POI)
- 8140 Joslin 138kV
- Technology
- Gas: 100 MW
- Total requested
- 100 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 1 February 2013
- Agreement signed
- 25 August 2016
- Proposed online date
- October 2017
- Came online
- October 2017
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem