GAS Β· ERCOT

Valley 1

Valley 1 is a 175 MW gas request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Apr 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0046
Grid region
ERCOT (Texas)
Developer
TXU Power
Connection point (POI)
VLSES_UNIT1 20.000
Technology
Gas: 175 MW
Total requested
175 MW
Study phase
FIS Complete
Queue status
Operational
Entered queue
3 April 2007

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem