OTHER Β· NYISO

PJM-Barrett HVDC

PJM-Barrett HVDC is a 650 MW other request withdrawn in the NYISO interconnection queue, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
134
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
TransEnergie US Ltd.
Connection point (POI)
Barrett 138 kV
Location
New York
Technology
Other: 650 MW
Total requested
650 MW
Queue status
Withdrawn
Entered queue
21 May 2003

Location

No county location in the queue data.

Power plants in New York Β· Transmission lines in New York

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem