WA Parish Addition is a 75.0 MW gas request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Nov 2011 (completed)
  2. ConsentedDec 2012 (completed)
  3. Construction (completed)
  4. OperatingJun 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
12INR0086
Grid region
ERCOT (Texas)
Developer
Petra Nova, LLC (NRG)
Connection point (POI)
WAP_PNPI_GT2 (110020)
Technology
Gas: 75.0 MW
Total requested
75.0 MW
Study phase
IA
Queue status
Operational
Entered queue
21 November 2011
Agreement signed
7 December 2012
Proposed online date
June 2013
Came online
June 2013

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem