ONSHORE WIND Β· ERCOT

McAdoo Energy Center

McAdoo Energy Center is a 300 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Sep 2006 (completed)
  2. ConsentedJan 2008 (completed)
  3. Construction (completed)
  4. OperatingTarget Aug 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
08INR0028
Grid region
ERCOT (Texas)
Developer
Invenergy
Connection point (POI)
MWEC_G1 34.500
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IA
Queue status
Operational
Entered queue
26 September 2006
Agreement signed
24 January 2008
Proposed online date
August 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem