SOLAR Β· ERCOT

Unruh Solar

Unruh Solar is a 151 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0464
Grid region
ERCOT (Texas)
Developer
BT Unruh Solar, LLC
Connection point (POI)
Tap 69kV 1785 BAGWELL1_9 β€šΓ„Γ¬ 1772 LAMARBM1_9
Technology
Solar: 151 MW
Total requested
151 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
18 July 2023
Proposed online date
December 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem