United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOStacy Solar
Stacy Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Greene County, New York, connecting to CenHud.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2014 (completed)
- Withdrawn / abandonedFeb 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 450
- Grid region
- NYISO (New York)
- Utility / transmission owner
- CenHud
- Developer
- Stacy Solar Center, LLC
- Connection point (POI)
- Coxsackie Substation 69kV
- Location
- Greene County, New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 20 August 2014
- Withdrawn
- February 2015
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Flint Mine SolarSolar Β· 100 MW Β· in study
- Greene County 1Solar Β· 20.0 MW Β· in study
- Greene County 2Solar Β· 10.0 MW Β· in study
- Athens GenGas Β· 1,080 MW Β· built
- Athens GenGas Β· 1,080 MW Β· built
- Leeds BESS ProjectBattery storage Β· 600 MW Β· withdrawn
- Athens Energy StorageBattery storage Β· 300 MW Β· withdrawn
- Athens Energy StorageBattery storage Β· 300 MW Β· withdrawn
- NY Catskill 0 Route 9W StorageBattery storage Β· 245 MW Β· withdrawn
- Kce NY 35Battery storage Β· 200 MW Β· withdrawn
- Hudson Energy StorageBattery storage Β· 200 MW Β· withdrawn
- Chateauguay BESSBattery storage Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem