United States β€Ί Grid β€Ί Interconnection queues

GAS Β· ERCOT

TXP Sealy G

TXP Sealy G is a 142 MW gas request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0055
Grid region
ERCOT (Texas)
Developer
TXP Holdings
Connection point (POI)
44255 Foster 138kV
Technology
Gas: 142 MW
Total requested
142 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
22 October 2013
Proposed online date
May 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem