United States βΊ Grid βΊ Interconnection queues
GAS Β· ERCOTSPC Henderson Option 2
SPC Henderson Option 2 is a 478 MW gas request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2012 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 17INR0002
- Grid region
- ERCOT (Texas)
- Developer
- Southern Power Company
- Connection point (POI)
- tap both Trinidad (#3124) βΓΓ¬ Tricorn (#2432), 38.5 mi from Tricorn, and Trinidad (#3123) βΓΓ¬ Watmill (#2427), approx. 49.9 miles away from Watmill.
- Technology
- Gas: 478 MW
- Total requested
- 478 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 4 September 2012
- Proposed online date
- June 2019