SOLAR · PJM

Pear Street Solar

Pear Street Solar is a 2.4 MW solar request built and operating in the PJM interconnection queue, in Atlantic County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Jun 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-041
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Absecon 12.47 kV
Location
Atlantic County, New Jersey
Technology
Solar: 2.4 MW
Total requested
2.4 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
18 June 2019
Proposed online date
March 2022
Came online
May 2020

Location

Marker shows the centre of Atlantic County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Atlantic County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem