SOLAR Β· ERCOT

BRP Springbok Solar

BRP Springbok Solar is a 202 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0091
Grid region
ERCOT (Texas)
Developer
Antelope Solar LLC
Connection point (POI)
23920 Blackwater Draw Switching Station 345kV
Technology
Solar: 202 MW
Total requested
202 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
25 August 2021
Proposed online date
December 2027
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem